[Construction Case] KT&G OO Factory

Test Operation Process of New Production Line

  • 슬러지(점도 30,000) 약 120톤 기존 협력·외부 업체, 위탁 반출·감량·건조 가능 업체 없음

밀폐 다단로 건조처리 의뢰

  • No expansion of wastewater treatment facilities due to economic feasibility and other reasons
  • Construction treatment service contract

운영 결과

  • Installation of one sealed multi-stage dryer in KT & OO plant
  • Completed successful processing with approximately 35 days of drying operation