[Construction Case] KT&G OO Factory
Test Operation Process of New Production Line
- About 120 tons of sludge (viscosity 30,000) No existing cooperation/external companies or companies that can be taken out, reduced, or built on consignment
Request for dry treatment of sealed multistage furnace
- No expansion of wastewater treatment facilities due to economic feasibility and other reasons
- Construction treatment service contract
Operational Results
- Installation of one sealed multi-stage dryer in KT & OO plant
- Completed successful processing with approximately 35 days of drying operation